How we work

How a project runs
with Boxco Builders

Four stages, one team. The same process runs whether the project is a 3 BHK apartment in Karnataka or a six-bedroom plantation home in Kerala. Only the scale changes.

01

Listen & Survey

A long first conversation, a site visit and a measured drawing of what is there. We learn how you live or how you want your guests to feel. We walk the plot, note slope, drainage, light direction and surrounding context, and ask far more questions than we answer at this stage. The output is a written brief that you sign off, plus a measured base drawing of the existing site or property.

Typical duration: 1 to 3 weeks, depending on travel and survey access.

02

Design & Cost

Concept drawings, 3D walk-throughs, material samples and a fully itemised budget. You sign off knowing what every line costs and why. We present at least two concept directions for the brief and then converge to a final design through structured feedback rounds. Material samples are physically presented in the studio or couriered to you, never decided from a render alone.

Typical duration: 6 to 14 weeks, depending on scope and approvals.

03

Build & Detail

Our project manager runs the site. Civil work, joinery, services, finishes and procurement run on one timeline, with weekly photos and updates if you live away. You get a named site manager, a shared project log, and a payment schedule tied to verifiable milestones, not arbitrary dates. Joinery is fabricated in our workshop and installed on site, which keeps the finish quality consistent across projects.

Typical duration: 45 to 90 days for an apartment fit-out, 10 to 20 months for a new-build home.

04

Hand Over & Aftercare

Keys, a building manual and a snag list closed in writing. We stay on call for the first year, because real homes need real settling-in. The manual covers materials used, paint codes, joinery hardware references and care notes, so a future repair or refresh is straightforward. Joinery warranties and service items are listed line by line.

Typical duration: Handover within 1 week of practical completion, aftercare for 12 months.

Typical project timelines

Plan around real numbers

Project type
Design
Build
Total
3 BHK apartment fit-out, Karnataka
4 to 6 weeks
45 to 90 days
3 to 5 months
4 BHK villa interior, Karnataka
6 to 10 weeks
90 to 150 days
5 to 7 months
3,000 sq ft new home, Kerala
8 to 12 weeks
10 to 14 months
12 to 17 months
5,000 sq ft plantation bungalow
10 to 16 weeks
14 to 20 months
17 to 24 months
12 to 15 key boutique resort
14 to 20 weeks
18 to 24 months
22 to 28 months